Mining Stock News – Ivanhoe Mines (TSX: IVN) Issues Third Quarter 2022 Financial Results, and Review of Mine Construction and Exploration Activities

Johannesburg, South Africa – November 14, 2022 (Newsfile Corp.) (Investorideas.com Newswire) Ivanhoe Mines’ (TSX: IVN) (OTCQX: IVPAF) President Marna Cloete and Chief Financial Officer David van Heerden are pleased to present the company’s financial results for the nine months ended September 30, 2022. Ivanhoe Mines is a leading Canadian mining company developing and operating its four principal mining and exploration projects in Southern Africa: expanding the operations of the world-class Kamoa-Kakula Mining Complex in the Democratic Republic of Congo (DRC); building the tier-one Platreef palladium, rhodium, nickel, platinum, copper and gold development in South Africa; restarting the historic, ultra-high-grade Kipushi zinc-copper-lead-germanium mine in the DRC; as well as exploring the expansive exploration licences of Ivanhoe’s Western Foreland for copper discoveries adjacent to Kamoa-Kakula. All figures are in U.S. dollars unless otherwise stated.

HIGHLIGHTS

The Kamoa-Kakula Mining Complex produced 97,820 tonnes of copper in concentrate during the third quarter of 2022, up from 87,314 tonnes in Q2 2022 and 55,602 tonnes in Q1 2022. Kamoa-Kakula has produced approximately 274,115 tonnes of copper year-to-date as of October 31, 2022.
During the third quarter, Kamoa-Kakula sold 93,812 tonnes of payable copper and recognized revenue of $460.5 million, with an operating profit of $222.8 million and an EBITDA of $254.4 million.
Kamoa-Kakula’s cost of sales per pound (lb.) of payable copper sold was $1.05/lb. for Q3 2022, compared with $1.15/lb. and $1.08/lb. in Q2 2022 and Q1 2022, respectively. Cash costs (C1) per pound of payable copper produced totalled $1.43/lb., compared to $1.42/lb. and $1.21/lb. in Q2 2022 and Q1 2022, respectively. Cash costs (C1) per pound of payable copper produced for the first nine months of 2022 total $1.38/lb.
During September and October, Kamoa-Kakula’s annualized production rate was more than 400,000 tonnes of floated and filtered copper, with this rate periodically exceeded over 24-hour periods during the third quarter.
Kamoa-Kakula’s previously announced de-bottlenecking program is approximately 70% complete and is tracking ahead of schedule. The program, will increase the combined processing capacity of the Phase 1 and 2 concentrator plants from 7.6 million tonnes per annum to approximately 9.2 million tonnes per annum. Once complete in Q2 2023, the rate of copper production is projected to reach approximately 450,000 tonnes per annum.
Kamoa-Kakula Mining Complex milled approximately 2.1 million tonnes of ore during the quarter at an average grade of 5.6% copper, compared to 2.0 million tonnes of ore at an average grade of 5.4% copper in Q2 2022.
Ivanhoe Mines recorded a profit of $23.9 million for Q3 2022, compared with a profit of $351.5 million and $85.4 million during Q2 2022 and Q3 2021, respectively. The quarterly profit includes Ivanhoe Mines’ share of profit and finance income from the Kamoa-Kakula joint venture of $74.9 million for Q3 2022.
Ivanhoe Mines has a strong balance sheet with cash and cash equivalents of $663.3 million as at September 30, 2022, and expects that Kamoa-Kakula’s operating and expansion capital expenditures on Phase 3 will continue to be funded from copper sales and additional facilities at the Kamoa-Kakula joint venture.
Ivanhoe Mines further increases the lower end of its 2022 production guidance range for Kamoa-Kakula to between 325,000 and 340,000 tonnes of copper in concentrate following the early commissioning of the Phase 2 expansion.
Given ongoing cost pressures experienced during the second and third quarters, largely related to logistics costs, the company is tightening its full-year C1 cash cost guidance to between $1.35/lb. and $1.40/lb. (previously $1.20/lb. to $1.40/lb.).
The basic engineering design for Kamoa-Kakula’s Phase 3 expansion is complete, with the results to be included in the updated technical report that will be released early in the new year.
Earthworks excavation for the Phase 3 mine, concentrator and direct-to-blister flash smelter is advancing as planned.
Lateral underground mine development on Platreef’s 950-metre-level, towards the location of the first ventilation shaft position, progressed well during the quarter. More than 300 metres of lateral development has been completed since work commenced in April 2022.
Construction of Platreef’s first solar-power plant commenced during the quarter, with commissioning expected in the second half of 2023. The solar-generated power from the plant will be used for mine development and construction activities, as well as for charging Platreef’s battery-powered underground mining fleet.
After quarter end, Ivanhoe Mines was granted 80 square kilometres of new, highly prospective exploration rights, known as the “Mokopane Feeder”, adjacent to the company’s Platreef Project in the Bushveld Complex, South Africa.
In September 2022, Ivanhoe Mines and G?camines hosted a breaking-ground ceremony at the Kipushi mine, marking the start of surface construction activities.
Early works in preparation for the start of underground mining at Kipushi were completed in August 2022. This included the refurbishment of key mining excavations, as well as blasting of the truck tip turning bay and truck passing bays on the 1,150-metre-level.

Full-year 2022 production and cost guidance revised

Management anticipates that the early commissioning of the Phase 2 concentrator plant in April 2022, approximately four months ahead of schedule, as well as the strong operating performance to date, has enabled Kamoa-Kakula to further increase the lower end of its full-year 2022 production guidance from a range of between 310,000 to 340,000 tonnes of copper in concentrate, to between 325,000 and 340,000 tonnes.

Given ongoing cost pressures experienced during the second and third quarters, largely related to logistics costs, the company is tightening its full-year C1 cash cost guidance to between $1.35/lb. and $1.40/lb. (previously $1.20/lb. to $1.40/lb.).

Cash costs (C1) is a non-GAAP measure used by management to evaluate operating performance and includes all direct mining, processing, and general and administrative costs. Smelter charges and freight deductions on sales to the final port of destination (typically China), which are recognized as a component of sales revenues, are added to C1 cash cost to arrive at an approximate cost of delivered finished metal.

Ivanhoe Mines’ President Marna Cloete commented:

“This is an incredibly transformational time for Ivanhoe Mines as construction activities advance at Kamoa-Kakula’s Phase 3 expansion and smelter, as well as at Platreef and Kipushi. We aim to build on the impressive track record we’ve developed from Kamoa-Kakula, where both Phase 1 and 2 were constructed on budget and ahead of schedule.

“I am extremely proud of the operating team at Kamoa-Kakula, who have continued to exceed expectations and are on track to meet the upper end of our original full-year production guidance.

“Alongside the majority of the mining industry, we have experienced inflationary pressures throughout this year. These pressures have been mostly logistics-specific, as Kamoa-Kakula’s on-site costs have been well managed and stable. Great progress has been made by the team at Kamoa-Kakula, working with our joint-venture partners, offtake partners and the Democratic Republic of Congo government, in implementing initiatives to remove the logistical bottlenecks experienced during the year. We expect to reap a positive impact from this hard work over the coming quarters.

“Our team remains focused on the strong value-creation opportunities in our project pipeline and I believe we’ll emerge stronger than ever following this period of global volatility. We are extremely confident in copper’s mid- to long-term fundamentals as the world navigates the transition to clean energy.”

Ivanhoe Mines to host a conference call for investors on November 14

The company will hold an investor conference call to discuss the Q3 2022 financial results at 10:30 a.m. Eastern time / 7:30 a.m. Pacific time on November 14. The conference call dial-in is +1-416-764-8650 or toll-free 1-888-664-6383, quote “Ivanhoe Mines Q3 2022 Financial Results” if requested. Media are invited to attend on a listen-only basis.

Link to join the live audio webcast: https://app.webinar.net/YvWzpn3maEn

An audio webcast recording of the conference call, together with supporting presentation slides, will be available on Ivanhoe Mines’ website at www.ivanhoemines.com.

After issuance, the Financial Statements and Management’s Discussion and Analysis will be available at www.ivanhoemines.com and www.sedar.com.

Principal projects and review of activities

Kamoa-Kakula Mining Complex
39.6%-owned by Ivanhoe Mines
Democratic Republic of Congo

The Kamoa-Kakula Mining Complex, operated as the Kamoa Holding joint venture between Ivanhoe Mines and Zijin Mining, has been independently ranked as the world’s fourth-largest copper deposit by international mining consultant Wood Mackenzie. The project is approximately 25 kilometres west of the town of Kolwezi and about 270 kilometres west of Lubumbashi. Kamoa-Kakula Mining Complex’s Phase 1 concentrator began producing copper in May 2021 and achieved commercial production on July 1, 2021. The Phase 2 concentrator, which doubled nameplate production capacity, was commissioned in April 2022.

Ivanhoe sold a 49.5% share interest in Kamoa Holding Limited (Kamoa Holding) to Zijin Mining and a 1% share interest in Kamoa Holding to privately-owned Crystal River in December 2015. Kamoa Holding holds an 80% interest in the project. Since the conclusion of the Zijin transaction, each shareholder has been required to fund expenditures at Kamoa-Kakula in an amount equivalent to its proportionate shareholding interest. Ivanhoe and Zijin Mining each hold an indirect 39.6% interest in Kamoa-Kakula, Crystal River holds an indirect 0.8% interest, and the DRC government holds a direct 20% interest.

Kamoa-Kakula took delivery of new large-scale underground equipment (MT65 haul truck and ST18 Scooptram) from Epiroc of Norsborg, Sweden. The new equipment aims to assist in improving underground productivity.

Health and safety at Kamoa-Kakula

At the end of September 2022, Kamoa-Kakula reached 2.46 million work hours free of a lost-time injury and had a Total Recordable Injury Frequency Rate (TRIFR) (total injuries recorded per 1,000,000 hours worked) of 1.73 for the nine months ended September 30, 2022.

Kamoa-Kakula regretfully reported a fatal accident in September 2022. The fatal accident occurred in a development area at the underground Kansoko Mine when a fall of ground struck a Kamoa-Kakula employee. Kamoa-Kakula is undertaking a comprehensive internal investigation into the accident and is working with the DRC authorities to facilitate their investigation of the accident. Kamoa-Kakula continues to strive toward its workplace objective of zero harm to all employees and contractors.

The projects construction team at Kamoa-Kakula conducted in-depth, onsite training on advanced risk assessment techniques through an accredited training institution. A group of 120 managers, supervisors and safety officers participated in the training program.

Kamoa-Kakula undertaking optimization of logistics costs

Kamoa-Kakula and other regional operators have experienced delays and increased logistics costs due to a shortage of available trucks, border congestion and occasional work action by truck drivers. Kamoa-Kakula is working alongside its offtake partners, Zijin Mining, CITIC Metal and Trafigura, as well as the government of the DRC, to undertake initiatives to optimize the transportation of Kamoa-Kakula’s products.

These initiatives include working with Kamoa-Kakula’s offtake partners, logistics service providers and local entrepreneurs to increase regional trucking capacity, improve processes for clearing products for export and the opening of new border crossings between the DRC and Zambia. Kamoa-Kakula is also continuing to explore the optionality of using a greater number of ports for exporting concentrate. These include Durban in South Africa, Dar es Salaam in Tanzania, Walvis Bay in Namibia and Beira in Mozambique, and longer-term the port of Lobito in Angola.

Cost pressures associated with logistics have occurred since Kamoa-Kakula’s Phase 2 concentrator declared commercial production four months ahead of schedule in early Q2 2022. While concentrate production doubled, this was not met with a sufficient supply of trucking capacity and this led to an increase in trucking contractor market pricing. In addition, the Lualaba Copper Smelter was closed in June for maintenance. This further increased trucking demand.

Under normal operating conditions, the cycle time of trucking concentrate from the mine gate to the port of Durban, and back, is approximately 45 days. Congestion experienced in the past two quarters saw this cycle time increase to as high as 70 days. This, in turn increased trucking demand by an additional 50%, further pushing up trucking contractor market pricing. The cycle time is shorter for the ports of Dar es Salaam, Walvis Bay and Beira.

Two new commercial DRC-Zambia border crossings opened, helping to reduce logistics bottleneck

During September, the operating hours of the Kasumbalesa border, located in Haut-Katanga province, were increased from 6 hours to 12 hours. The extended operating hours are expected to be permanent. Earlier in the quarter, congestion at the Kasumbalesa border crossing saw extended queues, which caused delays in customs clearing. Delays from congestion often incur additional charges.

During the third quarter, two new commercial border crossings opened on the DRC-Zambia border. A border crossing at Sakania, located approximately 150 kilometres by road southeast of Kasumbalesa, opened for commercial exports and imports. In addition, the Mokambo border crossing, located half way between Kasumbalesa and Sakania opened for commercial imports.

Reopening of Lualaba Copper Smelter in September reduces trucking demand

The Lualaba Copper Smelter, located approximately 50 kilometres from the Kamoa-Kakula Mining Complex, completed its scheduled maintenance in early September and the transportation of copper concentrates to the facility recommenced shortly thereafter. While undergoing scheduled maintenance, Kamoa-Kakula’s concentrate production was wholly transported and exported as a copper concentrate (approximately 50% contained copper), without the expected quantity of blister copper (approximately 99% contained copper), thereby temporarily increasing logistics volumes and costs for the quarter. The restart of the Lualaba Copper Smelter will assist in reducing overall shipping volumes, as the export of blister copper incurs lower logistics costs per unit compared to copper concentrate. The Lualaba Copper Smelter is expected to treat approximately 120,000 tonnes of copper concentrates from Kamoa-Kakula in 2022.

The increased opening hours of the Kasumbalesa border crossing, the opening of a new commercial export border crossing at Sakania, the resumption of blister copper shipments from the Lualaba Copper Smelter, as well as increased availability of trucks, is expected to ease congestion over the coming quarters.

A step-change improvement in cash costs of between 10% and 20% is anticipated once the Phase 3, 500,000-tonne-per-annum, direct-to-blister flash smelter is commissioned, expected by the end of 2024. A significant part of the reduction in cash costs, on a per tonne basis, is a result of the trucks hauling ~99% pure blister copper, instead of ~50% contained copper concentrate. Therefore, truck demand for hauling copper products to port is expected to decrease from current levels once the smelter is in operation. In addition, the smelter will generate valuable by-product credits from the sale of sulphuric acid, which is in structural deficit in the DRC Copperbelt.

Kakula Mine optimization work targeting grades towards 6% copper

Ongoing mining optimization work at the Kakula Mine successfully targeted higher head grades during the third quarter, to increase head grades up to 6% copper. Kamoa-Kakula continues to evaluate additional material handling capacity at the Kakula Mine to increase mining rates to feed the de-bottlenecked Phase 1 and 2 processing capacity of 9.2 million tonnes per year. Further details will be incorporated into the Phase 3 expansion pre-feasibility study, scheduled for release early in 2023.

While the near-term expansion of underground infrastructure at Kakula takes place, ore is being drawn from the surface stockpiles to maximize copper production as the Phase 1 and 2 concentrators are currently operating at more than design capacity. As of the end of September 2022, Kamoa-Kakula’s high- and medium-grade ore surface stockpiles totalled approximately 4.2 million tonnes at an estimated grade of 4.15% copper for a total of over 174,000 tonnes of contained copper.

Installation of additional underground conveying capacity at the Kakula South decline will increase the output of ultra-high-grade ore to the surface from the Kakula mine.

Record quarterly production of 97,820 tonnes of copper in Q3 2022

Kamoa-Kakula’s Phase 1 and 2 concentrator plants milled approximately 2.1 million tonnes of ore during the third quarter at an average feed grade of 5.6% copper, up from 1.95 million tonnes at an average grade of 5.4% copper in the second quarter. This included high-grade, run-of-mine ore from the Kakula Mine, supplemented with ore from the surface stockpiles to meet the throughput over design capacity. In line with design parameters, copper recoveries averaged approximately 86% during the quarter.

The Kamoa-Kakula Mining Complex set a new quarterly production record in the third quarter of 2022, with 97,820 tonnes of copper in concentrate produced, up from 87,314 tonnes produced in the second quarter and 55,602 tonnes produced in the first quarter. Kamoa-Kakula produced a total of 240,736 tonnes of copper in concentrate in the nine months ending September 30, 2022. Subsequent to quarter end, during the month of October Kamoa-Kakula produced a further 33,379 tonnes of copper.

The Phase 1 and 2 milling and flotation circuits continue to operate in excess of design capacity. At the end of October, there was also an additional 5,786 tonnes of floated, but not yet filtered, copper in the circuit. This marks the second month in a row that floated and filtered copper production from the Kamoa-Kakula Mining Complex has exceeded 400,000 tonnes per annum on an annualized basis.

The difference between floated, and subsequently, filtered copper arises from the current bottleneck in concentrate thickening and filter capacity at the tail end of the processing circuit. Excess floated copper is currently being temporarily stored as a slurry in a fully-lined pond adjacent to the Phase 1 and 2 concentrators. The unfiltered copper in inventory will be reclaimed into the concentrate thickener and filter press once capacity is expanded following the installation of a new concentrate thickener and Larox filter press, as part of the ongoing de-bottlenecking program.

All figures are on a 100% project basis and metal reported in concentrate is before refining losses or deductions associated with smelter terms. Guidance involves estimates of known and unknown risks, uncertainties and other factors, which may cause the actual results to be materially different.

Phase 1 and Phase 2 debottlenecking project to boost throughput to 9.2 million tonnes of ore per year is tracking ahead of schedule

Kamoa-Kakula’s previously announced de-bottlenecking program is approximately 70% complete and is tracking ahead of schedule. The program will increase the combined design processing capacity of the Phase 1 and 2 concentrator plants from 7.6 million tonnes per annum to approximately 9.2 million tonnes per annum

The de-bottlenecking program is targeting completion in the second quarter of 2023 and will boost Kamoa-Kakula’s annual production to approximately 450,000 tonnes of copper in concentrate by the second quarter of 2023, positioning Kamoa-Kakula as the world’s fourth largest copper producer.

Figure 1: Kamoa-Kakula’s base-case, pro-forma Phase 3 copper production (after de-bottlenecking of Phase 1 and 2 is complete) relative to the world’s projected top 10 producing mines in 2022 by payable copper production.

Source: Wood Mackenzie (April 2022). Note: Kamoa-Kakula production of 600 kt copper in concentrate is based on expected Phase 1, 2 and 3 steady-state production, following the de-bottlenecking of both Phase 1 and 2 concentrators, and commercial ramp-up of the Phase 3 concentrator.

Civil works on site are effectively complete with structural steel and plate work erection ongoing and electrical and mechanical installation well underway.

Planned plant shutdowns to install the new equipment required for the de-bottlenecking program are scheduled to take place between December 2022 and January 2023, with the aim to minimize any negative effects on production. Civil works on site are nearing completion with structural steel and plate work erection ongoing and electrical and mechanical installation now underway.

Aerial view of the additional concentrate thickener at Kamoa-Kakula’s Phase 1 and 2 concentrator plants that is under construction as part of the de-bottlenecking program.
Construction is progressing well in advance of the installation of the fourth Larox filter press at Kamoa-Kakula’s concentrate warehouse..

Phase 3 box-cut and basic engineering complete, procurement and construction activities have commenced

Construction of the twin declines to the Kamoa 1 and Kamoa 2 underground mines and excavation to access Phase 3 mining areas is advancing well.

Basic engineering design for the Phase 3 underground mine infrastructure, 5-million-tonne-per-annum concentrator plant and associated infrastructure is now complete. Detailed engineering, procurement and early construction activities are advancing well.

Earthworks for the concentrator plant and surface infrastructure is advancing on schedule, with the contract for the civil construction awarded and site preparation underway. Equipment fabrication is also ongoing.

Tenders for structural steel supply have been received and are in the process of being adjudicated.

Following the commissioning of Phase 3, expected by the end of 2024, Kamoa-Kakula will have a total processing capacity of more than 14 million tonnes per annum. The completion of Phase 3 is expected to increase copper production capacity to approximately 600,000 tonnes per annum. This production rate will position Kamoa-Kakula as the world’s third-largest copper mining complex, and the largest on the African continent (see Figure 1).

Kamoa-Kakula’s Phase 3 expansion includes a 500,000-tonne-per-annum, direct-to-blister flash smelter to produce approximately 99% pure copper metal, and the replacement of Turbine #5 at the Inga II hydroelectric power station. The turbine replacement will supply an additional 178 megawatts (MW) of clean hydroelectric power to the national grid and provide power for Phase 3.

Earthworks at the smelter site situated adjacent to Kamoa-Kakula’s Phase 1 and Phase 2 concentrator plants are approximately 70% complete with civil construction activities currently underway.

Detailed engineering is well advanced with orders for the bulk of the long lead items of equipment placed. Equipment and structural steel fabrication are currently underway.

The Kamoa-Kakula smelter uses technology supplied by Metso Outotec of Espoo, Finland, and meets the International Finance Corporation’s (IFC) emissions standards. The smelter has been sized to process most of the copper concentrate forecast to be produced by Kamoa-Kakula’s Phase 1, Phase 2, and Phase 3 concentrators, while any remaining copper concentrate may be smelted locally.

To read more about Ivanhoe Mines’ financial results: https://www.newsfilecorp.com/release/144113

About Ivanhoe Mines

Ivanhoe Mines is a Canadian mining company focused on advancing its three principal projects in Southern Africa: the development of major new, mechanized, underground mines at the Kamoa-Kakula copper discoveries in the Democratic Republic of Congo and the Platreef palladium-rhodium-nickel-platinum-copper-gold discovery in South Africa; and the extensive redevelopment and upgrading of the historic Kipushi zinc-copper-germanium-silver mine, also in the Democratic Republic of Congo.

Information Contact

Investors

Vancouver: Matthew Keevil +1.604.558.1034

London: Tommy Horton +44 7866 913 207

Media

Tanya Todd +1.604.331.9834

Website www.ivanhoemines.com

Forward-looking statements

Certain statements in this release constitute “forward-looking statements” or “forward-looking information” within the meaning of applicable securities laws. Such statements and information involve known and unknown risks, uncertainties and other factors that may cause the actual results, performance or achievements of the company, its projects, or industry results, to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information. Such statements can be identified using words such as “may”, “would”, “could”, “will”, “intend”, “expect”, “believe”, “plan”, “anticipate”, “estimate”, “scheduled”, “forecast”, “predict” and other similar terminology, or state that certain actions, events, or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved. These statements reflect the company’s current expectations regarding future events, performance and results and speak only as of the date of this release.

Such statements include without limitation, the timing and results of: (i) statements regarding a de-bottlenecking program underway at Kamoa-Kakula to expand processing capacity of Phase 1 and Phase 2 concentrators by 21%, to a combined total of 9.2 million tonnes of ore per annum; (ii) statements regarding copper production from Kamoa-Kakula’s first two phases is projected to reach 450,000 tonnes per annum by Q2 2023; (iii) statements regarding the expectation that the extended operating hours at the Kasumbalesa border will be permanent; (iv) statements regarding the Lualaba Copper Smelter is expected to treat approximately 120,000 tonnes of copper concentrates from Kamoa-Kakula in 2022; (v) statements regarding the increased opening hours of the Kasumbalesa border crossing, the opening of a new commercial export border crossing at Sakania, the resumption of blister copper shipments from the Lualaba Copper Smelter, as well as increased availability of trucks, is expected to ease congestion; (vi) statements regarding a step-change improvement in cash costs of between 10% and 20% is anticipated once the Phase 3 500,000-tonne-per-annum, direct-to-blister flash smelter is commissioned, expected by the end of 2024; (vii) statements that the smelter will generate valuable by-product credits from the sale of sulphuric acid, which is in structural deficit in the DRC Copperbelt; (viii) statements regarding the installation of additional underground conveying capacity is nearing completion at the Kakula South decline, which will increase output of ultra-high-grade ore to surface from the Kakula mine; (ix) statements regarding the de-bottlenecking program is on track to boost Kamoa Copper’s annual production to approximately 450,000 tonnes of copper in concentrate by the second quarter of 2023; (x) statements that following the commissioning of Phase 3, expected by the end of 2024, Kamoa-Kakula will have a total processing capacity of more than 14 million tonnes per annum; (xi) statements that the completion of Phase 3 is expected to increase copper production capacity to approximately 600,000 tonnes per annum and that this production rate will position Kamoa-Kakula as the world’s third-largest copper mining complex, and the largest on the African continent; (xii) statements regarding the turbine replacement will supply an additional 178-megawatts (MW) of clean hydroelectric power to the national grid, and provide power for Phase 3 and that the refurbishment is scheduled for completion in Q4 of 2024; (xiii) statements regarding the Kamoa Center of Excellence and that it will be a world-class facility, developed on the outskirts of Kolwezi, offering degrees, diplomas and short courses in collaboration with internationally accredited institutions; (xiv) statements that the Kamoa Centre of Excellence will take place over multiple phases to allow for departments, as well as sports facilities, to be added over time; (xv) statements that Management continues to anticipate that with the early commissioning of the Phase 2 concentrator plant, Kamoa-Kakula will be able to deliver the upper end of its original 2022 copper production guidance of 290,000 to 340,000 tonnes; (xvi) statements regarding off-site concentrate transportation and logistics charges, which is projected to ease slightly in the fourth quarter as a result of the resumption in operation of the Lualaba Copper Smelter and as Kamoa Copper and its partners implement logistical optimizations; (xvii) statements that cash costs is projected to come in at the upper end of the guidance range, subject to logistics costs easing in the fourth quarter; (xviii) statements regarding Platreef’s Phase 1 concentrator plant first production on track for Q3 2024; (xix) statements regarding the construction of Platreef’s first solar-power plant commenced in Q3 2022 with commissioning expected in 2023 and that the solar-generated power from the plant will be used for mine development and construction activities, as well as for charging Platreef’s battery-powered underground mining fleet; (xx) statements regarding Platreef’s 10-metre diameter Shaft 2, which will be the among the largest hoisting shafts on the African continent; (xxi) statements regarding the pilot drilling required for the raise bore center hole of Platreef’s Shaft 2 and the commencement of the sliding of the headframe are both planned to commence before the end of 2022; (xxii) statements regarding the expanded senior debt facility of up to $150 million providing Platreef with further optionality in terms of project financing, and limit potential equity contributions for Platreef’s Phase 1 development; (xxiii) statements regarding discussions to finalize the expanded Platreef senior debt facility with the view to it being completed in the new year; (xxiv) statements regarding the water requirement for Platreef’s Phase 1 operation is projected to peak at approximately three million litres per day, which will then increase to nine million litres per day once the Phase 2 expansion is complete; (xxv) statements regarding Ivanplats undertaking a commitment to complete the partially constructed Masodi Wastewater Treatment Works, which was halted in 2018 and that Ivanplats anticipates spending approximately ZAR 215 million ($13 million) to complete the works; (xxvi) statements that Ivanplats will purchase the treated water at a reduced rate of ZAR 5 per thousand litres; (xxvii) statements regarding the bulk power project at Platreef being scheduled for completion in Q4 2023; (xxviii) statements regarding implementation of the Platreef Project’s second Social and Labour Plan (SLP); (xxix) statements that Kipushi will be the world’s highest-grade major zinc mine, with an average grade of 36.4% zinc over the first five years of production; (xxx) statements regarding the new agreement signed between Kipushi Holding and G?camines to return the ultra-high-grade Kipushi Mine back to commercial production; (xxxi) statements that the Kipushi concentrator plant is scheduled to be complete by Q3 2024; (xxxii) statements that a new commercial border crossing will provide a significant advantage to the Kipushi Mine as a direct means of importing materials and consumables, as well as clearing customs and exporting products from the mine, and will provide socio-economic benefits to the town and Province of Haut-Katanga; (xxxiii) statements regarding the opening of the Kipushi border crossing also is anticipated to provide ancillary benefits to Kamoa-Kakula; (xxxiv) statements that mining at Kipushi will be performed using highly productive, mechanized methods and cemented rock fill will be utilized to fill open stopes; (xxxv) statements regarding 50 boreholes of potable water are planned to be drilled around the Kipushi district over the next five years, to reach areas not served by current distribution; (xxxvi) statements that all Phase 1 and Phase 2 operating costs and most Phase 3 capital expenditure at Kamoa-Kakula are expected to be funded from copper sales and facilities in place; (xxxvii) statements that the company has forecast to spend $94 million on further development at the Platreef Project; $69 million on development at the Kipushi Project; and $12 million on corporate overheads for the remainder of 2022; (xxxviii) statements regarding exploration activities at the Western Foreland exploration project in the DRC and other targets will continue in 2022 with an initial budget of $12 million for the remainder of 2022 on Western Forelands and $5 million on other targets; (xxxix) statements that Kamoa-Kakula’s operating and expansion capital expenditures on Phase 3 will continue to be funded from copper sales and additional facilities at the Kamoa-Kakula joint venture; (xl) statements that an updated technical report on Kamoa-Kakula’s Phase 3 expansion will be released early in the new year; (xli) statements regarding planned plant shutdowns to install the new equipment required for the de-bottlenecking program are scheduled to take place between December 2022 and January 2023, with the aim to minimize any negative effects on production; (xlii) statements regarding ore being drawn as required from Kamoa-Kakula’s stockpile to maximize copper production, as the concentrators are currently operating at more than the design capacity; (xliii) statements regarding the Inga II damn refurbishment project being complete in Q4 2024, with the engineering for the remaining equipment items and the ordering of replacement components expected to be completed early in 2023; (xliv) statements regarding enrollment at the Kamoa Centre of Excellence to commence in 2023; and (xlv) statements regarding Kamoa-Kakula possibly using a greater number of ports for exporting concentrate.

As well, all of the results of the feasibility study for the Kakula copper mine, the Kakula-Kansoko 2020 pre-feasibility study and the updated and expanded Kamoa-Kakula Mining Complex preliminary economic assessment, the Platreef 2022 feasibility study, and the Kipushi 2022 feasibility study constitute forward-looking statements or information and include future estimates of internal rates of return, net present value, future production, estimates of cash cost, proposed mining plans and methods, mine life estimates, cash flow forecasts, metal recoveries, estimates of capital and operating costs and the size and timing of phased development of the projects.

Furthermore, concerning this specific forward-looking information concerning the operation and development of the Kamoa-Kakula, Platreef and Kipushi projects, the company has based its assumptions and analysis on certain factors that are inherently uncertain. Uncertainties include: (i) the adequacy of infrastructure; (ii) geological characteristics; (iii) metallurgical characteristics of the mineralization; (iv) the ability to develop adequate processing capacity; (v) the price of copper, nickel, zinc, platinum, palladium, rhodium and gold; (vi) the availability of equipment and facilities necessary to complete development; (vii) the cost of consumables and mining and processing equipment; (viii) unforeseen technological and engineering problems; (ix) accidents or acts of sabotage or terrorism; (x) currency fluctuations; (xi) changes in regulations; (xii) the compliance by joint venture partners with terms of agreements; (xiii) the availability and productivity of skilled labour; (xiv) the regulation of the mining industry by various governmental agencies; (xv) the ability to raise sufficient capital to develop such projects; (xvi) changes in project scope or design; (xvii) recoveries, mining rates and grade; (xviii) political factors; (xviii) water inflow into the mine and its potential effect on mining operations, and (xix) the consistency and availability of electric power.

This release also contains references to estimates of Mineral Resources and Mineral Reserves. The estimation of Mineral Resources is inherently uncertain and involves subjective judgments about many relevant factors. Estimates of Mineral Reserves provide more certainty but still involve similar subjective judgments. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability. The accuracy of any such estimates is a function of the quantity and quality of available data and of the assumptions made and judgments used in engineering and geological interpretation (including estimated future production from the company’s projects, the anticipated tonnages and grades that will be mined and the estimated level of recovery that will be realized), which may prove to be unreliable and depend, to a certain extent, upon the analysis of drilling results and statistical inferences that ultimately may prove to be inaccurate. Mineral Resource or Mineral Reserve estimates may have to be re-estimated based on: (i) fluctuations in copper, nickel, zinc, platinum group elements (PGE), gold or other mineral prices; (ii) results of drilling; (iii) metallurgical testing and other studies; (iv) proposed mining operations, including dilution; (v) the evaluation of mine plans after the date of any estimates and/or changes in mine plans; (vi) the possible failure to receive required permits, approvals and licences; and (vii) changes in law or regulation.

Forward-looking statements and information involve significant risks and uncertainties, should not be read as guarantees of future performance or results and will not necessarily be accurate indicators of whether such results will be achieved. Many factors could cause actual results to differ materially from the results discussed in the forward-looking statements or information, including, but not limited to, the factors discussed above and under the “Risk Factors”, and elsewhere in the company’s MD&A for the three and nine months ended September 30, 2022, as well as unexpected changes in laws, rules or regulations, or their enforcement by applicable authorities; the failure of parties to contracts with the company to perform as agreed; social or labour unrest; changes in commodity prices; and the failure of exploration programs or studies to deliver anticipated results or results that would justify and support continued exploration, studies, development or operations. Although the forward-looking statements contained in this news release are based upon what management of the company believes are reasonable assumptions, the company cannot assure investors that actual results will be consistent with these forward-looking statements. These forward-looking statements are made as of the date of this news release and are expressly qualified in their entirety by this cautionary statement. Subject to applicable securities laws, the company does not assume any obligation to update or revise the forward-looking statements contained herein to reflect events or circumstances occurring after the date of this news release.

The company’s actual results could differ materially from those anticipated in these forward-looking statements because of the factors set forth below in the “Risk Factors” section in the company’s MD&A for the three and nine months ended September 30, 2022.

More Info:

This news is published on the Investorideas.com Newswire – a global digital news source for investors and business leaders

Disclaimer/Disclosure: Investorideas.com is a digital publisher of third party sourced news, articles and equity research as well as creates original content, including video, interviews and articles. Original content created by investorideas is protected by copyright laws other than syndication rights. Our site does not make recommendations for purchases or sale of stocks, services or products. Nothing on our sites should be construed as an offer or solicitation to buy or sell products or securities. All investing involves risk and possible losses. This site is currently compensated for news publication and distribution, social media and marketing, content creation and more. Disclosure is posted for each compensated news release, content published /created if required but otherwise the news was not compensated for and was published for the sole interest of our readers and followers. Contact management and IR of each company directly regarding specific questions.

More disclaimer info: https://www.investorideas.com/About/Disclaimer.asp Learn more about publishing your news release and our other news services on the Investorideas.com newswire https://www.investorideas.com/News-Upload/ and tickertagstocknews.com

Global investors must adhere to regulations of each country. Please read Investorideas.com privacy policy: https://www.investorideas.com/About/Private_Policy.asp

Gold-MiningStocks.com – investing ideas in gold and mining stocks

Like Gold Stocks? View our Gold / Mining Stocks Directory

What's your reaction?

Excited
0
Happy
0
In Love
0
Not Sure
0
Silly
0

You may also like

Leave a reply

Your email address will not be published. Required fields are marked *

More in:Latest News